Hywind Tampen
Hywind Tampen is the world’s first floating wind farm built to power offshore oil and gas platforms. Located approximately 140 km off the Norwegian coast in the North Sea, the project consists of 11 floating wind turbines with a total capacity of 88 MW, which makes it the world’s largest floating wind farm.
The project included the installation of 19 suction anchors and 33 mooring lines.
Semar played a key role alongside DOF Subsea in the planning and execution of the tow and hook-up operations for Equinor’s Hywind Tampen floating wind turbines.
Semar was responsible for designing and fabricating an innovative seafastening solution for the suction anchors. The design was developed with the intention that welding of the anchors would not be required during interim mobilizations. This solution demonstrated significant effectiveness during the operation by reducing anchor mobilization time by at least 50%.
Our personnel were onboard Skandi Iceman, contributing as Offshore Manager, Tow Master, and Lead Engineers during the installation phase. Thanks to thorough planning and solid engineering, the operation was carried out safely and efficiently—demonstrating the strength of our team and approach in complex offshore projects.
Scope of work summary
- Planning and engineering of base operations for the offshore scope
- Planning and engineering of anchor and mooring pre-installation
- Planning of tow and hook-up
- Establishing procedures and task plans for mobilisation, mooring pre-installation and tow and hook-up
- Motion analysis for grillage design
- Analysis for grillage and sea fastening of suction anchors
- Lift and hook-up analysis
- Offshore stationkeeping
- Installation aids and rigging design
Key figures
Client: Equinor/KDS JV (AKSO and DOF Subsea)
Project duration: 2020 – June 2023
Semar manhours on approx. 26 000 hrs.
Project characteristics: Offshore planning, personnel delivery, and execution of marine operations for the installation of suction anchors and the tow and hook-up of wind turbines.
Semar projects roles: Mobilisation Base coordinators, Offshore Managers, Tow Managers and Lead Engineer
“Semar supported DOF and Aker Solutions for the tow and hook-up planning and marine operation scope for Hywind Tampen project. Their contribution was vital to the overall success for these operations on Hywind Tampen. Semar demonstrating high focus on safety and in-depth technical understanding of their scope.
If external marine support is needed, Semar is a player to consider.” (Equinor)