GTA Hub Installation

BP launched a new business region to explore and develop hydrocarbon resources offshore Mauritania and Senegal, in partnership with Kosmos Energy. As part of the initial development phase, an inshore LNG hub was constructed, featuring a 1.1 km breakwater made of 18–21 concrete caissons. BOA was contracted to transport and float off the caissons using the semi-submersible barge Boabarge 33.

 

Semar provided the engineering and methodology for the offshore float-off of the concrete caissons. This included the design and analysis of the air bag separation system used to launch the caissons from Boabarge 33, ensuring safe and controlled operations at sea.

 

Scope of work summary

  • Concept development for airbag damping system
  • Naval Analyses and Procedures for the float off
  • Supervision during mobilization
  • Supervision during offshore operation
  • Delivery of Ship launching Airbag system

Key figures

Contractor: Boa Offshore AS

Client: Eiffage Génie Civil Marine.

Company: BP Plc and Kosmos Energy

Project characteristics: Offshore float off and installation of 21 caissons weighing 16500 each

Project duration: 2019 – 2022

Offshore campaigns: 2021-2022 in Dakar Senegal

Semar man hours: 2459

 
Eggedosis AS

Design som styrker merkevaren din!

Eggedosis.no

https://www.eggedosis.no
Previous
Previous

KNM Helge Ingstad frigate salvage